Ring Rail Kivistö-Lapinkylä MRU2

Destination Vantaa
Description Kivistö-Lapinkylä MRU2, which is a part of the Kehärata project, includes the building of approx. 1 000 m of new track structures downwards from the EV-surface. Project also includes approx. 700 m of concrete structured trough’s and approx. 330 m of retaining wall. Approx. 30 000 m3rtr of concrete works and in total approx. 2 500 tons of reinforcement steel, in which the share of steel fiber is approx. 600 tons, also approx. 3 000 m3ktr of rock excavation.
Contractor's Project Manager Jorma Härkönen 050-3112385
Client Liikennevirasto
Discipline Railway track
Contract time 05/2012 - 08/2014
Contract price M 20,6 €
Contract form Fixed Price Contract